0 |
Project Planning |
Scope of project, development of documents and materials for project overview, oversight, and project launch |
June 25-July 13, 2012 |
|
I |
Project Orientation and Launch |
Project kickoff meeting with FWISD steering committee and project team |
July 17, 2012 |
|
I |
Data Collection Activities, Interviews and Focus Groups |
Complete interviews and focus groups to develop functional requirements for the RFP to procure a new district Student Information System |
July 17-19, 2012
August 14-16, 2012 |
|
I |
Functional Requirements I to Project Team |
Functional requirements part I delivered to Project Team for review |
August 3, 2012 |
|
I |
Functional Requirement Part I Review |
Project Team reviews Part I of the functional requirements |
August 6-7, 2012 |
|
I |
Needs Analysis |
Development of functional requirements and performance specifications |
July 17-August 16, 2012 |
|
I |
Functional Requirements to Project Team |
Functional requirements part II delivered to Project Team for review |
August 20, 2012 |
|
I |
Functional Requirements Part II Review |
Project Team reviews Part II of the functional requirements |
August 21-22, 2012 |
|
I |
RFP Draft |
Request for Proposal Final Draft presented to FWISD |
August 24, 2012 |
|
I |
RFP Development |
CELT and FWISD complete RFP |
August 27-28, 2012 |
|
I |
RFP Released |
CELT and FWISD publicly release the Student Information System Request for Proposal |
August 29, 2012 |
|
I |
Pre-Proposal Vendor Conference |
CELT and FWISD conduct a pre-proposal vendor conference to clarify RFP changes and to answer vendor questions |
September 5, 2012 |
|
I |
Compile Vendor Demo Scripts |
CELT and FWISD will develop and compile vendor demonstration scripts for the vendor demonstrations |
September 6-7, 2012 |
|
I |
RFP Close |
Request for Proposals closed |
September 28, 2012 |
|
II |
RFP Evaluation |
Request for Proposals evaluated by FWISD project team |
October 1-10, 2012 |
|
II |
Vendor Finalists Identified |
Three vendor finalists identified and presented to FWISD by CELT and project team for approval |
October 17, 2012 |
|
II |
Notify Vendor Finalists |
Notify Three Vendor Finalists of selection and demonstration schedule |
October 18, 2012 |
|
II |
Vendor Demos |
Vendor Demonstrations completed by the three selected finalists |
November 1-14, 2012 |
|
II |
Summarize Results
PPT and Report to FWISD |
PPT presentation and report summarizing vendor demos delivered and presented to FWISD recommending final vendor |
November 16, 2012 |
|
II |
Vendor Selected |
Final vendor selected |
November 19, 2012 |
|
II |
Negotiations with Selected Final Vendor |
Negotiate contract, pricing, and deliverables with selected final vendor |
November 19, 2012 – December 7, 2012 |
|
II |
Selected Vendor Presented to FWISD School Board |
Selected vendor presented to the FWISD school board for approval |
December 11, 2012 |
|
II |
Contract Complete with Selected Vendor |
Contract completed with selected vendor |
December 21, 2012 |
|
III |
Implementation Phase In at pilot schools |
Implementation of the solution to begin in January 2013, completing August 2013 |
January 2013-August 2013 |