Fort Worth ISD Begins Process to Select Student Information System

The Fort Worth ISD is working with the Center for Educational Leadership and Technology (CELT) in the selection process of the District’s Student Information System. 

“It is our obligation to find the best product out there to serve the Fort Worth ISD,” says Superintendent Walter Dansby.

CELT has begun the process of interviewing District personnel to determine requirements for the next student information system. The kickoff of the project began in July with three days of roundtable discussions.  Additional meetings will take place August 14-16.  If you have any opinions you’d like to share regarding this process or system requirements, contact your building principal or supervisor or Marcia.Formby@fwisd.org, Sue.Guthrie@fwisd.org or Kyle.Davie@fwisd.org.

Below is the timeline for the needs identification, selection and implementation of the Student Information System.  It’s divided into three phases, culminating with the successful implementation in the 2013-14 school year.

Phase

Activity

Deliverables

Date

0

Project Planning

Scope of project, development of documents and materials for project overview, oversight, and project launch

June 25-July 13, 2012

I

Project Orientation and Launch

Project kickoff meeting with FWISD steering committee and project team

July 17, 2012

I

Data Collection Activities, Interviews and Focus Groups

Complete interviews and focus groups to develop functional requirements for the RFP to procure a new district Student Information System

July 17-19, 2012

August 14-16, 2012

I

Functional Requirements I to Project Team

Functional requirements part I delivered to Project Team for review

August  3, 2012

I

Functional Requirement Part I Review

Project Team reviews Part I of the functional requirements

August 6-7, 2012

I

Needs Analysis

Development of functional requirements and performance specifications

July 17-August 16, 2012

I

Functional Requirements to Project Team

Functional requirements part II delivered to Project Team for review

August 20, 2012

I

Functional Requirements Part II Review

Project Team reviews Part II of the functional requirements

August 21-22, 2012

I

RFP Draft

Request for Proposal Final Draft presented to FWISD

August 24, 2012

I

RFP Development

CELT and FWISD complete RFP

August 27-28, 2012

I

RFP Released

CELT and FWISD publicly release the Student Information System Request for Proposal

August 29, 2012

I

Pre-Proposal Vendor Conference

CELT and FWISD conduct a pre-proposal vendor conference to clarify RFP changes and to answer vendor questions

September 5, 2012

I

Compile Vendor Demo Scripts

CELT and FWISD will develop and compile vendor demonstration scripts for the vendor demonstrations

September 6-7, 2012

I

RFP Close

Request for Proposals closed

September 28, 2012

II

RFP Evaluation

Request for Proposals evaluated by FWISD project team

October 1-10, 2012

II

Vendor Finalists Identified

Three vendor finalists identified and presented to FWISD by CELT and project team for approval

October 17, 2012

II

Notify Vendor Finalists

Notify Three Vendor Finalists of selection and demonstration schedule

October 18, 2012

II

Vendor Demos

Vendor Demonstrations completed by the three selected finalists

November 1-14, 2012

II

Summarize Results

PPT and Report to FWISD

PPT presentation and report summarizing vendor demos delivered and presented to FWISD recommending final vendor

November 16, 2012

II

Vendor Selected

Final vendor selected

November 19, 2012

II

Negotiations with Selected Final Vendor

Negotiate contract, pricing, and deliverables with selected final vendor

November 19, 2012 – December 7, 2012

II

Selected Vendor Presented to FWISD School Board

Selected vendor presented to the FWISD school board for approval

December 11, 2012

II

Contract Complete with Selected Vendor

Contract completed with selected vendor

December 21, 2012

III

Implementation Phase In at pilot schools

Implementation of the solution to begin in January 2013, completing August 2013

January 2013-August 2013

 

 -FWISD-

Follow Fort Worth ISD on Facebook and Twitter for the latest information about the District.

 


Fort Worth Independent School District | 100 N University Dr. | Fort Worth TX 76107 | Phone:817-871-2000 | Email: web@fwisd.org

The Fort Worth Independent School District does not discriminate on the basis of race, color, religion, national origin, sex, disability, sexual orientation, age, gender identity and expression, military/veteran status, in its programs and activities. The following person(s) has been designated to handle inquiries regarding the non-discrimination policies: June Davis, 504 Coordinator, 100 N University Dr., NW 250, Fort Worth, TX 76107, 817-814-2875, Rufino Mendoza, Title IX Coordinator, 100 N University Dr., NW 130-I, Fort Worth, TX 76107, 817-814-2793 or Carla Kaufman, Title VII Coordinator, 100 N University Dr., SW 206, Fort Worth, TX 76107, 817-814-2710.